Prime Minister Shehbaz Sharif has taken notice of repeated delays in procuring nearly Rs. 928 million worth of sports equipment and infrastructure for the 2027 South Asian Games, scheduled to be held in Islamabad from April 3 to 11.
The Pakistan Sports Board (PSB), which is responsible for upgrading facilities at the Pakistan Sports Complex, has repeatedly failed to finalize contracts for electronic timing devices, sound systems and three diesel generators, sources told ProPakistani.
Several procurement attempts through open competitive bidding and government-to-government arrangements have been cancelled over insufficient competition, eligibility concerns and questions about the technical capabilities of participating contractors.
The PSB first initiated open competitive bidding in March 2025. However, it managed to award only one contract, worth Rs. 591.334 million, for electronic scoreboards to a joint venture between Swallow International and MAKB. Other procurement processes were cancelled because of a lack of sufficient competition.
In July 2026, the board tried again through a government-to-government arrangement. However, NETC was the only bidder. The process was subsequently scrapped after the Pakistan Engineering Council clarified that NETC did not hold independent contractor registration or licensing.
Rs. 928 Million Contract Cancelled
The PSB launched another open bidding exercise in September 2026 but cancelled it on October 17, just two days before the scheduled deadline for bid submission. The technical and financial bids were not formally opened on the Electronic Public Procurement and Disposal System (EPADS).
The board subsequently approached the National Radio and Telecommunication Corporation (NRTC) and Pakistan Infrastructure Development Company Limited (PIDCL) for direct contracting.
NRTC declined, saying it could not complete the projects within the required timeframe. PIDCL, however, submitted a bid, prompting the PSB to issue it a Letter of Intent on October 27.
The proposed Rs. 927.758 million contract covered three projects: electronic timing equipment worth Rs. 309.695 million, sound amplification systems costing Rs. 365.193 million, and three diesel generators priced at Rs. 252.869 million.
However, the PSB withdrew the Letter of Intent in the first week of November following intervention by higher authorities. Questions were also raised about PIDCL’s institutional capacity and technical experience to deliver the specialized projects within the available time.
PSB Starts Procurement Process Again
PSB Director General Yawar Hussain said the board had made six attempts to award the projects through government-to-government arrangements.
He said approval had now been obtained from the Principal Accounting Officer and a fresh procurement exercise had been initiated through open competitive bidding.
The repeated cancellations have put the timeline for completing and testing the required facilities under pressure, with less than five months remaining before the South Asian Games begin.
The 14th South Asian Federation Games are expected to bring athletes from across the region to Islamabad in April 2027.