The estimated cost of 501 federal development projects has increased by Rs. 5.36 trillion over the past five years, reaching Rs. 8.98 trillion from an earlier estimate of Rs. 3.62 trillion.
The increase of more than 148 percent highlights the growing financial burden of development projects and raises questions about initial cost estimates, implementation delays and project management.
According to official documents, the Ministry of Water Resources recorded the largest increase. The estimated cost of its 34 projects jumped by Rs. 2.477 trillion, from Rs. 1.138 trillion to Rs. 3.615 trillion.
The National Highway Authority (NHA) recorded the second-largest increase. The estimated cost of its 49 projects rose by Rs. 1.401 trillion, reaching Rs. 2.514 trillion from Rs. 1.113 trillion.
Cost of Development Projects Rises Across Government Departments
The estimated cost of 76 projects concerning provinces and special areas increased from Rs. 399 billion to Rs. 1.063 trillion.
Under the Power Division, the combined cost of 34 projects rose from Rs. 223 billion to Rs. 360 billion.
The Higher Education Commission’s 76 projects recorded an increase from Rs. 159 billion to Rs. 249 billion. Meanwhile, the estimated cost of 16 projects under the Ministry of Education climbed from Rs. 46 billion to Rs. 107 billion.
The cost of five Finance Division projects increased from Rs. 20 billion to Rs. 32 billion. Similarly, 18 projects under the Ministry of Interior saw their combined estimated cost rise from Rs. 20 billion to Rs. 35 billion.
Railway development projects also became more expensive. The estimated cost of 23 projects increased from Rs. 177 billion to Rs. 330 billion.
Defense Development Projects See Major Cost Increases
The documents also show sharp increases in the estimated costs of defense-related projects.
The combined cost of 11 projects under the Ministry of Defence rose from Rs. 16 billion to Rs. 78 billion.
One project under the Defence Production Division recorded an even larger increase, with its estimated cost climbing from Rs. 274 million to more than Rs. 10 billion.
Elsewhere, the estimated cost of nine projects under the Ministry of Information doubled from Rs. 5 billion to Rs. 10 billion.
The cost of 14 projects under the Ministry of Planning increased from Rs. 12 billion to Rs. 30 billion, while five Revenue Division projects saw their combined estimated cost rise from Rs. 45 billion to Rs. 138 billion.
The overall increase means the government now faces a substantially higher estimated bill for the same portfolio of development projects. The figures also raise questions about how accurately projects were initially costed and how delays and implementation issues contributed to the revisions.