Work has started on connecting Thar coal mines to Pakistan’s national electricity grid, a project expected to reduce their electricity costs by more than 60 percent.

The contract has been awarded and the contractor has mobilized at the site. The government has set April 2028 as the new completion target, bringing it forward by around eight months from the original deadline.

The project will connect mining operations in Thar Block I and Block II to the grid through 132kV transmission lines from the Islamkot Grid Station. The connection will provide around 60 megawatts of electricity to the two mining sites.

Thar’s mining operations currently depend heavily on diesel-generated electricity, which costs around 33 cents per kilowatt-hour. The shift to grid electricity is expected to bring the cost down to 13 cents per unit.

The mines consume between 200,000 and 250,000 litres of diesel every day. Around 35,000 litres are used for dewatering operations alone. Replacing diesel with grid electricity is expected to reduce fuel expenses by approximately Rs. 25 million daily.

The project is also expected to lower coal production costs by around $0.70 per tonne and reduce annual carbon emissions by approximately 80,000 tonnes.

The development was discussed at a review meeting chaired by Federal Minister for Power Sardar Awais Ahmad Khan Leghari, with officials from the Thar Coal and Energy Board, Sindh Engro Coal Mining Company, Sino Sindh Resources Limited, the Power Division and Hyderabad Electric Supply Company in attendance.

Officials also informed the meeting that Thar Block I plans to add around 40 electric trucks to its mining operations by the end of this year. Block II is targeting the start of electric vehicle deployment in 2028, alongside the completion of its grid connection.